Q1 2021
Phase 1
Priority for close

The activities within this stream must be completed before the close date to comply with the agreement's security, access, or representation requirements.

Q4 2021
Phase 2
High dependency

These activities are the highest dependency items. Many other projects, activities, and streams are dependent on these activities to be completed. These activities can hold up other migration activities from commencing or ending.

Q1 2022   Q2 2022 - Q3 2022
Phase 3
Project streams

The project streams do not form dependencies on any other critical streams. This is because they are not on the critical path; however, they must be completed before the two-year mark of the agreement closes.

Q1 2021
Phase 1
Priority for close

The activities within this stream must be completed before the close date to comply with the agreement's security, access, or representation requirements.

Q4 2021
Phase 2
High dependency

These activities are the highest dependency items. Many other projects, activities, and streams are dependent on these activities to be completed. These activities can hold up other migration activities from commencing or ending.

Q1 2022   Q2 2022 - Q3 2022
Phase 3
Project streams

The project streams do not form dependencies on any other critical streams. This is because they are not on the critical path; however, they must be completed before the two-year mark of the agreement closes.